Once
the client makes his choice and the contracts are signed, the designer
and his staff begin the detailed design work--"the nuts and
bolts of the thing," says Fexas--which can comprise as many
as 40 drawings specifying every significant structure on the boat. Both
he and Gerr do this on a fast-track basis, scrambling to complete the
drawings necessary to get the builder started on the hull and superstructure,
then racing to stay ahead of construction. "There are a lot more
of them then there are of us," jokes Gerr, who works with two partners.
You
may think that from here onward the designers stay handcuffed to their
drafting tables. On the contrary, they are still actively looking out
for the interests of their clients. Fexas often works within a system
whereby stage payments made to the yard during the build are tied to specific
construction milestones, such as when the engines are landed on the engine
beds. His contract states that he must travel to the yard five or six
times to inspect and approve the yard's work up to each "construction
event" in order for the payments to be released. While Gerr doesn't
always work within so strict a structure, he still typically makes several
trips to the yard at critical stages of the building process to ensure
that construction is proceeding properly. In addition, every designer
fields countless phone calls clarifying issues for both the builder and
the client and working out conflicts to everyone's approval. Gerr
describes his role as that of a liaison between sometimes-conflicting
interests, with his ultimate responsibility being the satisfaction of
his client. Sea
trials are often the occasion for this final fulfillment. "I go
up especially to supervise a maneuvering trial, which includes recording
data for fuel consumption and speed, and to oversee an inclining experiment
to confirm stability characteristics against our initial numbers,"
says Gerr. He also says that even the finest yards can sometimes become
a little rushed toward the completion of a yacht, and it's good
to have a fresh set of eyes make sure "every edge has been sanded
smooth." It's
not only the client who's pleased on the day the boat is finished.
Gerr says that, in keeping with similar statistics for building architects,
for example, only about one out of eight boats a designer draws is ever
actually built. So when a well-made boat hits the water, the designer's
elation can rival the owner's. Our Spectator told me, "There's
no other thrill like starting with a sketch on a napkin, then developing
some real drawings, then seeing the boat come to life." Now that
doesn't sound cranky at all. Tom
Fexas Yacht Design Phone: (561) 287-6558. Fax: (561) 287-6810.
www.tomfexas.com. Gerr Marine Phone: (212) 864-7030. Fax: (212) 932-0872. Next page > Sketch, Part 2 > Page 1, 2, 3 |
||||||||||||||||||
This article originally appeared in the January 2003 issue of Power & Motoryacht magazine.














Brokerage Listings Powered by BoatQuest.com